Completed Duration Location Scope of project Contact details Customer #
100% Jul/2009 - Apr 2010

Najaf / Iraq

Supply of line pipes, pipe fitting, valves and crossing materials for Al-Najaf Depot Project (ECP Project) Ministry of Oil

SCOP

1
100% Apr/2010 - Dec/2010

Samawa / Iraq

Supply of line pipes, pipe fitting, valves and crossing materials for Al-Samawa Refinery (ECP Project) Ministry of Oil SCOP 2
100% Nov/2009 - Dec/2010

Basra / Iraq

Design & supply of 9 steel tanks of 25,000m3, 10,000m3 and 7,000m3 capacities for oil products Ministry of Oil SRC 3
100% May.2011- Jan. 2012

South Refinery-Basrah

execution of environmental impact Assessment (EIA) for upgrading FCC project in Basrah Refinery, include Topographical and Site Survey, EIA Study Ministry of Oil SRC 4
100% Mar/2008 - May/2011

North Iraq

Design & supply & supervision for 3 oily waste water treatment plants for 3 refineries Ministry of Oil NRC 5
100% May/2008 - Jun/2010

Babil / Iraq

Agriculture College,Babil University,21 Building Complex, total area 28,000m2 MHE MHE 6
100% Jul/2009 - Dec/2012

Basra / Iraq

Design, supply, & installation of 7 LPG tanks of 200 m3 capacities Ministry of Oil SRC 7
100% Dec/2004 – Oct /2010

Hawija / Iraq

Design and construction of Hawija WTP 44000m3/day, Kirkuk / Iraq (Turnkey)
The contract includes design & supply of the following (all pile foundation)
- Low lift pump house with suction well
- One flash mixer with receiving well
- Three clarifiers Ø34m       - Ten filters 40m2 each
-  Underground concrete storage tank of 4,000m3
- Power house diesel generator
-  Sludge pits                     - Chemical building
- Workshop building          - Admin & control building
- Two elevated (25m) steel storage tanks (½ & ¼ MG)
-  Laying water pipelines Ø500mm L3500m & Ø600mm L5500m
-  Supply & installations of all mechanical & electrical & control equipment
MMPW Water Directorate 8
100% Dec/2009 - Jun/2010 Najaf / Iraq Supply of ERW, LSAW Line Pipes, fittings and accessories Ministry of Oil SCOP 9
100% Feb/2007 – Apr/2008 Babil / Iraq Design, supply all construction materials for village service road of 29,100m for Babil Governorate. The project is composed of earth works, 25cm sub-base coarse, 10cm asphaltic concrete and 9 pipe culverts Babil Governorate Babil Gov. 10
100% Dec/2002 – Aug/2003

Abu Ghraib / Iraq

Design and construct elevated steel tank of 500,000 Gallon capacity, Supply & installation & testing & operation of the elevated steel tank. Bab Al-Muadham / Medan Square General Directorate for Water / Ministry of Municipality  and Public Works 11
100% Aug/2001 – Apr/2002 Al-Qaim / Iraq Construction of embankments and box culverts in south of Al-Qaim town to protect Al-Qaim town from rains Ministry of Irrigation State Commission for Maintenance of Irrigation Projects 12
100% Feb/2000 – Jan2002

Missan / Iraq

Survey, design and earth work embankment of (4.5 – 5m) average height and (18 – 20m) width of 12,660m village road will all the pipes and box culverts Palestine Street –Baghdad –Iraq Ministry of Irrigation 13
100% Aug/1999 – Jan/2001

Mosul / Iraq

Supply all the construction material, earth works, 30cm sub-base coarse and 20cm asphalt paving of 9,850m road to Al-MeshrakSulphure Company Nineveh Governorate Building, Al-Mosul – Iraq Nineveh Governorate 14
100% Aug/1999 - Jan/2000 Baghdad / Iraq Survey, design and earth work embankment of (4.5 – 5m) average height and (18 – 20m) width of 12,660m village road will all the pipes and box culverts Ministry of Planning Build Baghdad – Iraq Planning Committee 15
100% Sep/1998 – Feb/2001 Missan / Iraq Supply all the construction material, earth works, 30cm sub-base coarse and 20cm asphalt paving of 9,850m road to Al-MeshrakSulphure Company MHE State Organization for Roads and Bridges 16
100% Oct/1998 – Jul/1999 Al-Sakhriga / Iraq Survey, design and construct earth works and sub-base of 44,000m road between Emara and Al-Azear including pipe and box culverts Palestine Street –Baghdad –Iraq Ministry of Irrigation 17
100% Jan/2000 – Oct/2000 Salah-Al-Deen / Iraq Supply all the construction materials to contract 8 military stores of 24.4mx50.8m and 8m height with all the electrical installation and water networks in Tikreet Camp Salah Al-Deen Governorate Building Tikreet – Iraq Salah Al-Deen Governorate 18
100% Dec/2001 – Aug/2002 Abu Ghraib / Iraq  Design and construction of Abu Graib Water Treatment Plant WTP of 22,000m3/day composed of:
- Two clarifiers of 26m diameter
- One concrete storage tank of 2,000m3
- Ten Filters of 40m2 area each
- Pump house                                  - Flash mixer
- Receiving well 200m3 capacity      
- Power house 900kVA diesel generator.
- Sludge pit 100m3 capacity            -  Chemical building
- Workshop building                        - Transmission line
- Ductile Iron Pipe of 5.5km Ø600mm
- Elevated steel tank of 25m height and ½Million Gallon capacity
Bab Al-Muadham / Meedan Square

MMPW

General Corporation for Water & Sewage (GCWS) 19
100% Sep/2000 – Sep/2001

Basra / Iraq

Construction of fuel storage tanks foundations for Strategic Project Supply all concrete needed for the foundation for the storage tanks in 3groups in Basra / Fao – Basra Governorate of a capacity of 5000m3 (2×2000m3 + 1×1000m3) tanks, the work includes all the earth works and sub-base layers of 90cm thick

Basra Governorate Building / Basra/ Iraq Basra Governorate 20
100% May/2000 – Oct/2002 Thulueiya/ Iraq Al-Thulueiya Irrigation Project, Design & Construct irrigation Concrete channels, concrete regular box culverts and care bridge MMPW Water Directorate 21
100% Mar/1999 – Aug/2000 Salah Al-Deen / Iraq Tikret Sewerage Project. Design & supply all the concrete pipes of diameter 1,800mm for main sewage sewers with 32 manholes of height (2.00 – 6.5m) including repaving the roads with asphaltic concrete Bab Al-Muadham / Meedan Square MMPW General Corporation for Water & Sewage (GCWS) 22
100% Jun./2009- Dec./2009 Zubair South & North Rumila Field instruments for degassing station Ministry of Oil SOC 23
100% Sep./2009- Mar./2010

North Oil Company

Supplying cables & junction boxes Ministry of Oil NOC 24
100% Oct./2009 - Feb./2010 North Oil ompany supplying field instruments for gas compressor stations / AB-1, 3 & 8 Ministry of Oil NOC 25

100%

Mar/2010 - March/2017

Basra / Iraq

Design and construction of Muftiya WTP 2x1000m3/h, Basrah / Iraq (Turnkey)
The contract includes design & supply of the following (all pile foundation)
·  Low lift pump house with suction well
·  Intake structure with sheet pile in Shat Al-Arab
·  Two flash mixers
·  Four clarifiers Ø27m
·  Two intermediate pump houses
·  Twenty pressure filters Ø2.4x6.5m
·  Two steel storage tank of 5,000m3
·  Diesel pump house
·  Power house 2x600kVA diesel generator
·  Two Sludge pits 400m3 capacity
·  Two chemical buildings
·  Two workshop buildings
·   Admin & control building §  Two R.O. units 5m3/day

  SCOP 26

100%

Dec. 2008 – Oct. 2010

Hawija / Iraq

Design and construction of Hawija WTP 3000m3/h, Kirkuk / Iraq (Turnkey)
The contract includes design & supply of the following (all pile foundation)
·   Low lift pump house with suction well
·   One flash mixer with receiving well
·   Three clarifiers Ø34m
·   Ten filters 40m2 each
·   Underground concrete storage tank of 4,000m3
·   Power house diesel generator
·   Sludge pits
·   Chemical building
·   Workshop building
·   Admin & control building
·   Two elevated (25m) steel storage tanks (½ & ¼ MG)
·    Laying water pipelines Ø500mm L3500m & Ø600mm L5500m
·    Supply & installations of all mechanical & electrical & control equipment

Water Directorate / Ministry of Municipalities & Public Works

 

 

27

100%

May 2008 – Jun 2010

Babil / Iraq

Agriculture College, Babil University, 21 Building Complex, total area 28,000m2 Ministry of Higher Education  MHE 28

100%

Feb. 2007 – Apr. 2008

Babil / Iraq

Design, supply all construction materials for village service road of 29,100m for Babil Governorate. The project is composed of earth works, 25cm sub-base coarse, 10cm asphaltic concrete and 9 pipe culverts

Babil Governorate

Babil Governorate

29

100%

Dec. 2002 – Aug. 2003

Abu Ghraib / Iraq

Design and construct elevated steel tank of 500,000 Gallon capacity, Supply & installation & testing & operation of the elevated steel tank.

General Directorate for Water / Ministry of Municipality and Public Works   30
100% Dec. 2001 – Aug. 2002 Abu Ghraib / Iraq ·         Design and construction of Abu Graib Water Treatment Plant WTP of 22,000m3/day composed of:
·      Two clarifiers of 26m diameter
·      One concrete storage tank of 2,000m3
·      Ten Filters of 40m2 area each
·      Pump house
·      Flash mixer
·      Receiving well 200m3 capacity
·      Power house 900kVA diesel generator.
·      Sludge pit 100m3 capacity
·      Chemical building
·      Workshop building
·      Transmission line
·      Ductile Iron Pipe of 5.5km Ø600mm
·      Elevated steel tank of 25m height and ½Million Gallon capacity
General Corporation for Water & Sewage (GCWS) / Ministry of Municipality and Public Works   31

100%

Aug. 2001 – Apr. 2002 Al-Qaim / Iraq

Construction of embankments and box culverts in south of Al-Qaim town to protect Al-Qaim town from rains

State Commission for Maintenance of Irrigation Projects / Ministry of Irrigation   32
100% May 2000 – Oct. 2002 Thulueiya / Iraq Al-Thulueiya Irrigation Project, Design & Construct irrigation Concrete channels, concrete regular box culverts and care bridge Water Directorate / Ministry of Municipalities & Public Works   33
100% Feb. 2000 – Jan. 2002 Missan / Iraq Survey, design and earth work embankment of (4.5 – 5m) average height and (18 – 20m) width of 12,660m village road will all the pipes and box culverts Ministry of Irrigation Ministry of Irrigation 34
100% Jan. 2000 – Oct. 2000 Salah- Al-Deen / Iraq Supply all the construction materials to contract 8 military stores of 24.4mx50.8m and 8m height with all the electrical installation and water networks in Tikreet Camp Salah Al-Deen Governorate Salah Al-Deen Governorate 35
100% Aug. 1999 – Jan. 2001 Mosul / Iraq

Supply all the construction material, earth works, 30cm sub-base coarse and 20cm asphalt paving of 9,850m road to Al-Meshrak Sulphure Company

Nineveh Governorate Nineveh Governorate 36

100%

Aug. 1999 – Jan. 2000 Baghdad / Iraq

Supply all the asphaltic material needed for paving 21 KM asphaltic concrete binder and surface layer for roads in Al-Karkh side for planning committee

Planning Committee / Ministry of Planning Ministry of Planning 37

100%

Mar. 1999 – Aug. 2000

Salah Al-Deen / Iraq

Tikret Sewerage Project. Design & supply all the concrete pipes of diameter 1,800mm for main sewage sewers with 32 manholes of height (2.00 – 6.5m) including repaving the roads with asphaltic concrete

General Corporation for water & sewerage (GCWS) / Ministry of Municipality and Public Works Ministry of Municipality and Public Works 38

100%

Sep. 1998 – Feb. 2001 Missan / Iraq

Survey, design and construct earth works and sub-base of 44,000m road between Emara and Al-Azear including pipe and box culverts

State Organization for Roads and Bridges / Ministry of Housing and Construction Ministry of Housing and Construction 39
100%

Oct. 1998 – Jul. 1999

Al-Sakhriga / Iraq

Survey and design for embankment earth works of (3.8 – 4.3m) height and 22 – 25m) wide of 10,330m road to AL-Sakhriga village will all the pipes and box culverts

Ministry of Irrigation Ministry of Irrigation 40

SCOP :  State Company for Oil Projects               SRC   :   South Refineries Company.                NRC  :          North Oil Company.    