Projects

Projects

Projects


Projects
under Construction – By Al-Qabas Company



#



Client



Scope of project



Location



Duration



Start / End



%



Completed


1.
 


JV HDGSK ( Hundayi Co., GSE Co. & SK
Co.).


Karbala Refinery Project PKG 7


Karbala/Iraq


Sep/2015-May2018


58%


2.
 


JV HDGSK ( Hundayi Co., GSE Co. & SK
Co.).


Karbala Refinery Project PKG 8


Karbala/Iraq


April/2016-July2018


45%


3.
 


General Directorate of Water / Ministry
of Municipalities & Public Works


·


Design and construction of AL-SALAM &
AL-MANSOURIYA Water Treatment Plant
of
88,000m3/day composed of:


·


Intake structure


·


Low lift pump house


·


Flash mixer


·


Four clarifiers of 38m diameter


·


Twenty Filters of 40m2 area
each


·


Two concrete storage tank of 8,000m3
each


·


Two High lift Pump houses


·


Three Power buildings


·


Sludge pit 500m3 capacity


·


Chemical building


·


Workshop building


·


Admin building


·


3 operator houses


·


Engineer house


·


3 guard rooms


·


Fences


·


Elevated steel tank of 25m height and
1100m3 capacity


·


Transmission lines


§


Ductile pipe (double flange) Ø700mm,
length 350m.


§


Ductile pipe Ø500mm, length 300m.


§


Ductile pipe Ø1000mm, length 1250m.


§


Ductile pipe Ø600mm, length 12,800m.


§


Ductile pipe Ø900mm, length 27,600m.


§


Ductile pipe Ø500mm, length 4,000m.


§


Ductile pipe Ø300mm, length 1,000m.


§


Ductile pipe Ø700mm, length 13,400m.


§


Ductile pipe Ø500mm, length 4,200m.


§


Ductile pipe Ø800mm, length 500m.


Dyala / Iraq


Jan. 2013 – May 2017


52%


4.
 


General Directorate of Water / Ministry
of Municipalities & Public Works


·


Design and construction of AL-SADA & AL-GOBOR
Water Treatment Plant
of
44,000m3/day composed of:


·


Intake structure


·


Low lift pump house


·


Flash mixer


·


Three clarifiers of 34m diameter


·


Ten Filters of 40m2 area each


·


One concrete storage tank of 4,000m3


·


High lift Pump house


·


Two Power buildings


·


Sludge pit 400m3 capacity


·


Chemical building


·


Workshop building


·


Admin building


·


3 operator houses


·


Engineer house


·


3 guard rooms


·


Fences


·


Elevated steel tank of 25m height and
900m3 capacity


·


Transmission lines


§


Ductile Iron Pipe of 8km Ø500mm


§


Ductile Iron Pipe of 1.5km Ø250mm


§


Ductile Iron Pipe of 5.5km Ø400mm


§


Ductile Iron Pipe of 1.65km Ø700mm


§


Ductile Iron Pipe of 1.5km Ø500mm


Dyala / Iraq


Sep. 2012 – March. 2017


66%


 
PROJECTS
EXECUTED BY AL-QABAS COMPANY



#



Client



Scope of project



Location



Duration



Start / End



%



Completed


5.
 


JV HDGSK ( Hundayi Co., GSE Co. & SK
Co.).


Karbala Refinery Project PKG 7


Karbala/Iraq


Sep/2015-May2018


58%


6.
 


JV HDGSK ( Hundayi Co., GSE Co. & SK
Co.).


Karbala Refinery Project PKG 8


Karbala/Iraq


April/2016-July2018


45%


7.
 


General Directorate of Water / Ministry
of Municipalities & Public Works


·


Design and construction of AL-SALAM &
AL-MANSOURIYA Water Treatment Plant
of
88,000m3/day composed of:


·


Intake structure


·


Low lift pump house


·


Flash mixer


·


Four clarifiers of 38m diameter


·


Twenty Filters of 40m2 area
each


·


Two concrete storage tank of 8,000m3
each


·


Two High lift Pump houses


·


Three Power buildings


·


Sludge pit 500m3 capacity


·


Chemical building


·


Workshop building


·


Admin building


·


3 operator houses


·


Engineer house


·


3 guard rooms


·


Fences


·


Elevated steel tank of 25m height and
1100m3 capacity


·


Transmission lines


§


Ductile pipe (double flange) Ø700mm,
length 350m.


§


Ductile pipe Ø500mm, length 300m.


§


Ductile pipe Ø1000mm, length 1250m.


§


Ductile pipe Ø600mm, length 12,800m.


§


Ductile pipe Ø900mm, length 27,600m.


§


Ductile pipe Ø500mm, length 4,000m.


§


Ductile pipe Ø300mm, length 1,000m.


§


Ductile pipe Ø700mm, length 13,400m.


§


Ductile pipe Ø500mm, length 4,200m.


§


Ductile pipe Ø800mm, length 500m.


Dyala / Iraq


Jan. 2013 – May 2017


52%


8.
 


General Directorate of Water / Ministry
of Municipalities & Public Works


·


Design and construction of AL-SADA & AL-GOBOR
Water Treatment Plant
of
44,000m3/day composed of:


·


Intake structure


·


Low lift pump house


·


Flash mixer


·


Three clarifiers of 34m diameter


·


Ten Filters of 40m2 area each


·


One concrete storage tank of 4,000m3


·


High lift Pump house


·


Two Power buildings


·


Sludge pit 400m3 capacity


·


Chemical building


·


Workshop building


·


Admin building


·


3 operator houses


·


Engineer house


·


3 guard rooms


·


Fences


·


Elevated steel tank of 25m height and
900m3 capacity


·


Transmission lines


§


Ductile Iron Pipe of 8km Ø500mm


§


Ductile Iron Pipe of 1.5km Ø250mm


§


Ductile Iron Pipe of 5.5km Ø400mm


§


Ductile Iron Pipe of 1.65km Ø700mm


§


Ductile Iron Pipe of 1.5km Ø500mm


Dyala / Iraq


Sep. 2012 – March. 2017


66%


9.
 


State Company for Oil Projects SCOP


Design and construction of Muftiya WTP
2x1000m3/h, Basrah / Iraq
(Turnkey)


The contract includes design & supply of
the following (all pile foundation)


·


Low lift pump house with suction well


·


Intake structure with sheet pile in Shat
Al-Arab


·


Two flash mixers


·


Four clarifiers Ø27m


·


Two intermediate pump houses


·


Twenty pressure filters Ø2.4×6.5m


·


Two steel storage tank of 5,000m3


·


Diesel pump house


·


Power house 2x600kVA diesel generator


·


Two Sludge pits 400m3
capacity


·


Two chemical buildings


·


Two workshop buildings


·


Admin & control building


§


Two R.O. units 5m3/day


Basra / Iraq


Mar/2010 – March/2017


100%


10.
 


Water Directorate / Ministry of
Municipalities & Public Works


Design and construction of Hawija WTP
3000m3/h, Kirkuk / Iraq
(Turnkey)


The contract includes design & supply of
the following (all pile foundation)


·


Low lift pump house with suction well


·


One flash mixer with receiving well


·


Three clarifiers Ø34m


·


Ten filters 40m2 each


·


Underground concrete storage tank of
4,000m3


·


Power house diesel generator


·


Sludge pits


·


Chemical building


·


Workshop building


·


Admin & control building


·


Two elevated (25m) steel storage tanks
(½ & ¼ MG)


·


Laying water pipelines Ø500mm L3500m &
Ø600mm L5500m


·


Supply & installations of all mechanical
& electrical & control equipment


Hawija / Iraq


Dec. 2008 – Oct. 2010


100%


11.
 


Ministry of Higher Education


Agriculture College, Babil University,
21 Building Complex, total area 28,000m2


Babil / Iraq


May 2008 – Jun 2010


100%


12.
 


Babil Governorate


Design, supply all construction
materials for village service road of
29,100m for Babil Governorate. The
project is composed of earth works, 25cm
sub-base coarse, 10cm asphaltic concrete
and 9 pipe culverts


Babil / Iraq


Feb. 2007 – Apr. 2008


100%


13.
 


General Directorate for Water / Ministry
of Municipality and Public Works


Design and construct elevated steel tank
of 500,000 Gallon capacity, Supply &
installation & testing & operation of
the elevated steel tank.


Abu Ghraib / Iraq


Dec. 2002 – Aug. 2003


100%


14.
 


General Corporation for Water & Sewage (GCWS)
/ Ministry of Municipality and Public
Works


·


Design and construction of Abu Graib
Water Treatment Plant
WTP of
22,000m3/day composed of:


·


Two clarifiers of 26m diameter


·


One concrete storage tank of 2,000m3


·


Ten Filters of 40m2 area each


·


Pump house


·


Flash mixer


·


Receiving well 200m3 capacity


·


Power house 900kVA diesel generator.


·


Sludge pit 100m3 capacity


·


Chemical building


·


Workshop building


·


Transmission line


·


Ductile Iron Pipe of 5.5km Ø600mm


·


Elevated steel tank of 25m height and
½Million Gallon capacity


Abu Ghraib / Iraq


Dec. 2001 – Aug. 2002


100%


15.
 


State Commission for Maintenance of
Irrigation Projects / Ministry of
Irrigation


Construction of embankments and box
culverts in south of Al-Qaim town to
protect Al-Qaim town from rains


Al-Qaim / Iraq


Aug. 2001 – Apr. 2002


100%


16.
 


Water Directorate / Ministry of
Municipalities & Public Works


Al-Thulueiya Irrigation Project, Design
& Construct irrigation Concrete
channels, concrete regular box culverts
and care bridge


Thulueiya / Iraq


May 2000 – Oct. 2002


100%


17.
 


Ministry of Irrigation


Survey, design and earth work embankment
of (4.5 – 5m) average height and (18 –
20m) width of 12,660m village road will
all the pipes and box culverts


Missan / Iraq


Feb. 2000 – Jan. 2002


100%


18.
 


Salah Al-Deen Governorate


Supply all the construction materials to
contract 8 military stores of
24.4mx50.8m and 8m height with all the
electrical installation and water
networks in Tikreet Camp


Salah- Al-Deen / Iraq


Jan. 2000 – Oct. 2000


100%


19.
 


Nineveh Governorate


Supply all the construction material,
earth works, 30cm sub-base coarse and
20cm asphalt paving of 9,850m road to
Al-MeshrakSulphure Company


Mosul / Iraq


Aug. 1999 – Jan. 2001


100%


20.
 


Planning Committee / Ministry of
Planning


Supply all the asphaltic material needed
for paving 21 KM asphaltic concrete
binder and surface layer for roads in
Al-Karkh side for planning committee


Baghdad / Iraq


Aug. 1999 – Jan. 2000


100%


21.
 


General Corporation for water & sewerage
(GCWS) / Ministry of Municipality and
Public Works


Tikret Sewerage Project. Design & supply
all the concrete pipes of diameter
1,800mm for main sewage sewers with 32
manholes of height (2.00 – 6.5m)
including repaving the roads with
asphaltic concrete


Salah Al-Deen / Iraq


Mar. 1999 – Aug. 2000


100%


22.
 


State Organization for Roads and Bridges
/ Ministry of Housing and Construction


Survey, design and construct earth works
and sub-base of 44,000m road between
Emara and Al-Azear including pipe and
box culverts


Missan / Iraq


Sep. 1998 – Feb. 2001


100%


23.
 


Ministry of Irrigation


Survey and design for embankment earth
works of (3.8 – 4.3m) height and 22 –
25m) wide of 10,330m road to AL-Sakhriga
village will all the pipes and box
culverts


Al-Sakhriga / Iraq


Oct. 1998 – Jul. 1999


100%

 SCOP :
      State Company for Oil
Projects                  SRC   :          South
Refineries Company.

      NRC  :          North Oil
Company.                                MHE
:
           Ministry of Higher Education.

  MMPW:      Ministry of
Municipality & Public Works.